Installing wind turbines offshore has a number of advantages compared
to onshore development. Onshore, difficulties in transporting large
components and opposition due to various siting issues, such as
visual and noise impacts, can limit the number of acceptable locations
for wind parks. Offshore locations are usually far enough away from
populations to reduce objections from residents and can take advantage
of the high capacity of marine shipping and handling equipment,
which far exceeds the lifting requirements for multi-megawatt wind
turbines. In addition, the winds tend to blow faster and smoother
at sea than on land yielding more electricity generation per square
meter of swept rotor area. Especially larger onshore wind farms
tend to be in somewhat remote areas, so electricity must be transmitted
over long power lines to cities. Offshore wind farms can be closer
to coastal cities simplifying some transmission issues, yet far
enough away to reduce visual and noise impacts.
Good wind resource, proximity to load centers, and expansion of development
areas are some of the reasons why development of offshore wind energy
is moving forward. By the close of 2005, 804 MW of offshore wind power
plants were operating in Denmark, the Netherlands, Sweden, and United
Kingdom.
Challenges for offshore development include higher initial investment
costs for large machines and sea cables for the connection to land; more
difficult access to the turbines resulting in higher maintenance costs;
and more severe environmental conditions at sea due to salt water and
additional loads from waves and ice.
Despite the difficulties of offshore development, it holds great promise
for expanding wind generation capacity. In Europe, the space available
for offshore wind turbines in many countries is larger than onshore. For
example, in the Netherlands roughly 3 GW of wind power could be installed
in areas available outside the 12-mile zone (about 22 km) with a water
depth of less than 20 m. The Netherlands shares this advantage of shallow
water with countries such as Belgium, Denmark, Germany, and the United
Kingdom. Figure 1 below shows the cumulative installed offshore capacity
to by the end of 2005 on the basis of 925-MW of total installed capacity.

Figure
1 – Offshore Wind Projects Installed through 2005
Based on a Total of 804 MW
Need
to Collaborate Identified
Work is underway in many countries to address issues surrounding wind
development offshore. To identify what the critical research issues were
for offshore wind and to determine if a collaborative international research
opportunity existed, several meetings and workshops were held between
2003 and 2004. First, in October 2003 and again in October 2004, workshops
on deep-water technologies were held in Washington, D.C. with participants
from the US and Europe, see: http://www.nrel.gov/wind_meetings/offshore_wind/.
It was clear from these workshops that opening vast windy areas of deep-water
ocean for electric power generation will require development of new technologies
and strategies. Meanwhile in Europe, IEA Wind Annex XI sponsored a Topical
Experts Meeting (#43) on Critical Issues Regarding Offshore Technology
and Deployment in March 2004 in Denmark. The meeting gathered 18 participants,
representing Denmark, Finland, the Netherlands, Sweden, the United Kingdom,
and the United States. Presentations covered both detailed research presentations
and more general descriptions of current situations in Denmark, Finland,
the Netherlands, United Kingdom, and the United States. The result from
all of these meetings recommended the IEA Wind Implementing Agreement
as a framework for expanding international cooperation on critical research
activities pertaining to offshore wind energy.
Task 23 Approved
In May 2004, the IEA wind executive committee approved a proposed research
Annex to sponsor focused workshops and develop research tasks directed
at understanding issues and developing technologies to advance the development
of wind energy systems offshore.
The objectives of this annex are to do the following related to offshore
development of wind energy systems:
• Conduct R&D activities of common interest to participants
to reduce costs and uncertainties
• Identify joint research tasks among interested countries based
on the issues identified at the Topical Expert Meeting #43 on Critical
Issues Regarding Offshore Technology and Deployment
• Organize workshops on critical research areas for offshore wind
deployment. The goal of the workshops is to identify R&D needs of
interest to participating countries, publish proceedings, and define joint
research activities for the Annex participants.
During the first year of the Annex, (May 2004 to May 2005) the goal was
to identify interested participants, project leaders for each research
area, and prepare Work Programs and Budgets for each collaborative research
activity. Since then the annex membership has grown as shown in Table1.

OJECTIVES WITH PROPOSED SUBTASKS
This Task comprised of two subtasks with Risø National Laboratory in Denmark and the National Renewable Energy Laboratory in the United States serving as joint operating agents. Risø leads Subtask One: Experience with Critical Deployment Issues, and NREL will lead Subtask Two: Research for Deeper Water.
MEANS
TO ACHIEVE OBJECTIVES WITH PROPOSED SUBTASKS
This annex is comprised of two subtasks with Risø National Laboratory
in Denmark and the National Renewable Energy Laboratory in the United
States serving as joint operating agents. Risø will lead Subtask
One: Experience with Critical Deployment Issues, and NREL will lead Subtask
Two: Research for Deeper Water.
SUBTASK ONE: EXPERIENCE WITH CRITICAL DEPLOYMENT ISSUES
Denmark, through RISØ National Laboratory, will serve as operating
agent for this subtask, led by Jørgen Lemming. Workshops have been
planned in three research areas including:
Research Area 1: Ecological Issues and Regulations
Research Area 2: Electric System Integration
Research Area 3: External Conditions, Layouts and Design of Offshore Wind
Farms.
A volunteer host country will assume the responsibility for each research
area until formal research plans are adopted.
The Netherlands has agreed to host the first workshop for Research Area
1 (Ecological Issues And Regulations) but a meeting date has not yet been
set. The United Kingdon hosted the first workshop on Grid Interconnection
and the meeting was held at Manchester University 12-13 September 2005.
Denmark hosted the first workshop for Research Area 3 (External Conditions,
Layouts and Design of Offshore Wind Farms) held on December 2005 at RISØ
National Laboratory. A significant topic dealing with Operation and Maintenance
Issues was also considered a high priority topic but at this time there
are no plans to hold a workshop to cover this topic. Each research area
is described below:
Research Area 1: Ecological Issues and Regulations
The areas of collaboration to be discussed at the first workshop are:
|
•
|
Baseline
data and research methods |
|
o |
Develop
methods to share baseline data and research methods for pre- and post-construction
studies. |
|
• |
Impacts
on the environment (assessment criteria) |
|
o |
Summarize
preliminary conclusions from environmental impact assessments among
nations that have offshore facilities. (This area is similar to one
of the objectives of Concerted action for Offshore wind energy Deployment
[COD]. This annex will collaborate with these activities whenever
appropriate.) |
|
o |
Evaluate
potential cumulative effects to the marine ecology. |
|
o |
Compare
methodologies and preliminary conclusions from avian and mammal surveys. |
|
o |
Evaluate
streamlining of planning and approval procedures. |
|
o |
Educate
the regulators and facilitate interagency cooperation. |
• |
Pre-
and post-construction monitoring of operating wind facilities |
|
• |
Public
(stakeholder) involvement and acceptance |
• |
Decommissioning
processes and procedures. |
Research
Area 2: Electric System Integration
The first workshop in Research Area 2, discussed the technical options
and the role of enabling technologies in achieving reliable design of
offshore connections. This includes the development of offshore grids
for collection and transport of significant amounts of power to the shore
and the integration with the onshore transmission network.
Also, cost effective integration of offshore wind generation will require
the development of systematic and consistent approaches to resolving a
number of technical, commercial, and regulatory issues. These include
license conditions, offshore security standards, transmission charges,
grid code, connection and use of system codes, all of which were included
in the scope of the workshop.
Based on a number of presentations on experiences from existing offshore
wind farms and the planning process, the delegates at the workshop in
Manchester concluded that the following topics were the most important
for further work under Task 13:
|
• |
Offshore
wind meteorology and impact on power fluctuations and wind forecasting |
|
• |
Behavior
and modeling of high-voltage cable systems |
|
• |
Grid
Code and security standards for offshore versus onshore |
|
• |
Control
and communication systems of large offshore wind farms |
|
• |
Technical
architecture of offshore grid systems and enabling technologies. |
The working
title for the working groups covering the subjects is suggested to be:
Connection of Offshore Wind Farms to Onshore Grids.
Research Area 3: External Conditions, Layouts, and Design of Offshore
Wind Farms
The purpose of the workshop in Research Area #3 is to explore the key
issues and highlight the topics related to the following areas:
|
• |
Exchange,
validate, and evaluate wind resource data and wind maps specific to
regions with high potential for wind development. |
|
• |
Share
databases and innovations to enhance measurement accuracy of marine
buoys pertaining to long-term sea-state and MET-Ocean data. |
|
• |
Exchange
technical information of wave loading prediction methods and validation
experience of wave loading on wind turbine structures. |
|
• |
Share
experience with long-term measurement techniques and instrumentation
at offshore stations. |
|
• |
Evaluate
various turbine array configurations in large, closely spaced farms
and examine critical parameters such as mutual shadow wake effects,
affect on energy production, fatigue, and ultimate loading. |
|
• |
Exchange
technical experience with offshore forecasting to predict wind plant
output.
Each of these research areas will be narrowed in scope after a discussion
to identify appropriate areas for collaboration among annex participants. |
SUBTASK
TWO: RESEARCH FOR DEEPER WATER
The second subtask will address issues pertaining to deployment of wind
turbines in water depths greater than 30 m. This subtask is led by NREL,
with the primary research area focused on a Codes Comparison Collaborative
(OC3) that is sharing information, research, and data to advance the understanding
of models that can predict the behavior of support structures that deviate
from the present monopile technology.
Coupled turbine/substructure dynamic modeling - A Kick-off meeting was
held in October 2004 in Washington D.C. United States. Representatives
from Denmark, Japan, Norway, the United Kingdom, and the United States
attended. To maximize the benefit to the research community and to take
advantage of experience with current turbine modeling effort in shallow
water, it was decided to include both shallow and deep-water modeling.
Uncertainties associated with load prediction increase the risk for offshore
machines, and the development of accurate dynamic models for load prediction
is the best way to reduce these uncertainties. Participants will share
their codes among the other participants and compare assumptions, model
fidelity, and the results of model outputs for controlled cases determined
by the group. Through this type of rigorous sharing and subsequent validation
efforts, offshore researchers will accelerate the development of codes
for modeling a wide range of offshore wind turbines systems. A research
topic “Coupled turbine/substructure dynamic modeling” was
discussed and targeted for detailed collaborations and planning at a follow
up meeting held at Risø National Laboratory in Denmark in January
2005. The January meeting attracted 32 participants from 8 countries.
Results Expected
The results of the Subtasks One and Two in the first year are expected
to be the following. Technical proceedings will be published from the
workshops on critical research areas from the two Subtasks and made available
to member countries only through this website. In addition, the results
will be presented by the operating agents or their representatives to
various conferences and to the IEA Executive Committee. Collaborative
research activities under each Subtask will be defined with participating
members, work program, and budget. A project leader for each research
area will be designated who reports to one of the Operating Agents.
Time Schedule
The Annex shall continue for a period of four years beginning May 2004,
when it was approved in-principle in Chester, UK. The Annex may be extended
for such additional periods as may be determined by two or more participants,
acting in the Executive Committee and taking into account any recommendation
of the Agency’s Committee on Energy Research and Technology (CERT)
concerning the term of the Annex. Extensions shall thereafter only apply
to those Participants who agree to the extension. A preliminary time schedule
is provided below.
Participation
Participation is open to any organization within a country belonging to
the IEA Wind Implementing Agreement. No fees are required through May
2005. The United States and Denmark have agreed to bear the cost of shared
operating agents through 2005 and the participants in the planned workshops
bear their own costs. Fees for the coming years of operation will depend
on the research tasks identified and approved by participants.
Authors: Jørgen Lemming, Risø National Laboratory, Denmark
and
Walter Musial, NREL, United States.
|
| |
|
1. Critical
Deployment Issues
Password
Contact Information for
Subtask 1
2.
Research for Deeper Waters
Latest News
IEA Task 23 Offshore Wind Energy Deployment - Phase IV of the Offshore Code Comparison Collaborative (OC3)
Risø-DTU, Roskilde, Denmark March 13, 2009
Meeting Presentations
(password required)
|
Password
Contact Information for
Subtask 2
Offshore
Wind Experiences
IEA PUBLICATIONS
9, rue de la Fédération
75739 Paris Cedex 15
Printed in France by the IEA
June 2005, 25 pages.
This study has reviewed the experiences of the first series of
commercial-scale offshore wind installations. It concentrates on
the pioneering Northern European projects between 2000 and 2004.
It addresses all aspects of the barriers and achievements encountered
in these early developments. It has specifically involved five
offshore wind farms with interviews of key individuals associated
with those projects.
The report is available in pdf (free of charge) at
http://www.iea.org/textbase/papers/2005/offshore.pdf
Copenhagen Offshore
Wind Energy Conference Poster

|
|